The R&D Tax Credit rules
- A pre-filing notification is needed for accounting periods beginning on or after 1 January 2024 if the company has not claimed in any of the previous three accounting periods. It must be filed at least 90 days before the claim is made, through MyEnquiries under Corporation Tax (CT) / R&D Pre-filing Notification.
- The claim must be made on the Form CT1 through ROS within 12 months of the end of the accounting period in which the expenditure was incurred.
- On each Form CT1 the company specifies whether the instalment is to be treated as an overpayment of tax (offset) or paid. The first instalment specification is made on the return for the period of the expenditure; the second and third on the two following returns.
- No supporting documentation is filed with the return, but Revenue may request it afterwards to verify that the claim is a valid claim.
Documents that satisfy them
Upload whichever of these you hold. Dated records made during the period rate higher than reconstructions, and reconstructions rate higher than estimates.
- MyEnquiries submission record for Form 766C with date, where required
- Form CT1 as filed with the R&D panel, showing the pre-filing box ticked where applicable
- ROS filing acknowledgement showing the filing date against the 12-month deadline
- Board minute or written approval of the final figures and the instalment specifications
Red flags
These produce a Red flag rating on the related questions until they are cleared.
- No pre-filing notification where one was required, or filed fewer than 90 days before the claim
- Form CT1 claim filed more than 12 months after the end of the accounting period
Questions this evidence feeds
In the Ireland question set this topic supports the following questions. The sample rating shows how the fictional Cloonmore Diagnostics Ltd file scored on each.
- IE09Pre-filing notificationWhether the company needed to notify Revenue (first claim, or no claim in the previous three accounting periods) and, if so, whether Form 766C was sent through MyEnquiries at least 90 days before the claim was made.Strong
- IE10Form CT1 claim and instalment specificationsWhether the claim was made on the Form CT1 within 12 months of the end of the accounting period, whether the R&D panel is complete, and whether the specification for each instalment (offset or payment) was made on the right return.Strong
- IE12Accounting test reconciliation and record integrityWhether each line of the claim traces to the general ledger and the accounts with no general or admin expense lines, and whether records show their author and date of creation.Strong
See all twelve on Ireland draft audit questions. The questions are a simulation; nothing is sent to Revenue, and a rating is not a decision by Revenue.
Related
- Ireland payroll and staff cost evidenceIreland (Revenue Commissioners): What payroll, contract and pension records support staff costs in a claim.
- Ireland time allocation evidenceIreland (Revenue Commissioners): How staff time on R&D is recorded and apportioned, and what records support the split.
- Ireland project records evidenceIreland (Revenue Commissioners): Technical records that show the uncertainty, the work done and the results, dated as they happened.
- Ireland evidence checklistThe evidence a Ireland R&D Tax Credit claim should hold, by topic: payroll, time records, project records, contracts and calculations.