Ireland sample report
Risk report: Cloonmore Diagnostics Ltd
A complete mock audit result for a fictional Ireland company claiming under the Research and Development Corporation Tax Credit. Every name, figure and document on this page is invented.
Summary
Generated 20 November 2025EVIDENCE READINESS
68/100
- Strong
- 7 of 12
- Need work
- 3 of 12
- Red flags
- 2 of 12
A higher score means your evidence supports more of your answers.
- Company
- Cloonmore Diagnostics Ltd
- Programme
- Research and Development Corporation Tax Credit
- Authority
- Office of the Revenue Commissioners
- Period
- Accounting period ended 31 December 2024
- Claim
- Fictional claim of €640,000 qualifying expenditure under section 766C, giving a credit of €192,000 at 30 per cent
- Questions answered
- 12 of 12
The science files for both projects are well supported and the pre-filing notification and Form CT1 were filed in the right order and on time. The file is weakest on third-party costs and the grant deduction: two answers are contradicted or unsupported by the documents provided, and three rely on year-end estimates or incomplete analysis.
Question-by-question results
12 questions| Ref | Question | Evidence matched | Status |
|---|---|---|---|
| IE01 | Systematic, investigative or experimental activity Whether the work was planned and carried out in a logical sequence to a recognised methodology, with dated records of goals, progress, methods and conclusions rather than only outcomes. Both projects show a planned sequence of experiments with dated records of the work done, not only the results. | Project plans for Projects A and B; dated bench-test logs; weekly engineering notes | Strong |
| IE02 | Field of science or technology and category of R&D Whether each project is placed in a field listed in S.I. No. 434 of 2004 and classified as basic research, applied research or experimental development, with the reasoning recorded. Each project is placed in medical engineering under S.I. No. 434 of 2004 and classified as experimental development with reasons. | Science file Tab A for each project | Strong |
| IE03 | Advancement sought and uncertainty resolved Whether the scientific or technological advancement sought and the uncertainty to be resolved are stated for each project, and when the uncertainty was resolved so that the R&D phase has an end date. The advancement and uncertainty are stated per project and the memo fixes the date the cartridge tolerance uncertainty was resolved. | Science file Tabs A and F; resolution memo dated 14 October 2024 | Strong |
| IE04 | State of knowledge and competent professional What was done before the project began to show that the advance was not already achieved or available to a competent professional in the field, and the qualifications and experience of the project manager and team. The team's qualifications are documented, but the literature and prior-art search said to have been done in January 2024 was not saved and cannot now be recreated. | CVs of the project lead and three engineers; no saved search results | Needs work |
| IE05 | Emoluments and time apportionment How the emoluments of staff carrying on R&D were calculated, how the proportion of time spent on qualifying activity was determined and recorded, and who reviewed the split. Emoluments trace to payroll, but the time percentages were set at year end by the finance manager with no timesheets or tracker records behind them. | Payroll export; year-end percentage schedule | Needs work |
| IE06 | Wholly and exclusively costs Whether overheads, materials, rent, cloud computing and plant or machinery were apportioned on a reasonable basis to the R&D activity and the method documented, with costs after the R&D phase excluded. Rent, light and heat were apportioned at 40 per cent with no note of the basis, and cloud costs include a general company subscription. | Overhead schedule | Needs work |
| IE07 | Subcontracted R&D and written notification For payments to universities, institutes of higher education or unconnected third parties, whether the greater-of 15 per cent or €100,000 limits were applied separately, and whether each subcontractor was notified in writing that it may not claim the credit. The payment exceeds the greater of 15 per cent of the company's own R&D spend (€76,500) or €100,000, and there is no record that the university was told in writing it may not claim the credit. | University of Galway research agreement and invoices for €130,000; no written notification | Red flag |
| IE08 | Grant-funded expenditure excluded Whether expenditure met directly or indirectly by grant or other assistance from the State, the EU, an EEA state, the UK or another state was deducted, and whether the Form CT1 figures are net of that assistance. The grant letter is on file but the qualifying expenditure on the Form CT1 was not reduced by the grant-assisted amount. | Enterprise Ireland R&D grant letter for €90,000; CT1 figures gross | Red flag |
| IE09 | Pre-filing notification Whether the company needed to notify Revenue (first claim, or no claim in the previous three accounting periods) and, if so, whether Form 766C was sent through MyEnquiries at least 90 days before the claim was made. The company had not claimed before; the notification was filed more than 90 days before the Form CT1 was filed on 19 September 2025. | MyEnquiries record for Form 766C dated 2 June 2025 | Strong |
| IE10 | Form CT1 claim and instalment specifications Whether the claim was made on the Form CT1 within 12 months of the end of the accounting period, whether the R&D panel is complete, and whether the specification for each instalment (offset or payment) was made on the right return. The claim was made within 12 months of the period end, the pre-filing box is ticked and the first instalment is specified as an overpayment for offset. | Form CT1 filed 19 September 2025; ROS acknowledgement; R&D panel extract | Strong |
| IE11 | Qualifying company, location and group Whether the company is within the charge to Irish corporation tax, where the R&D was carried on (Ireland, EEA or UK), whether the expenditure is deductible elsewhere, and how group expenditure was allocated under the 51 per cent group rules. The company is within the charge to Irish corporation tax, all work was carried on in Galway and it is not a member of a group. | Certificate of incorporation; lease for the Galway premises; single-company confirmation | Strong |
| IE12 | Accounting test reconciliation and record integrity Whether each line of the claim traces to the general ledger and the accounts with no general or admin expense lines, and whether records show their author and date of creation. Every line traces to a general ledger code, there are no general expense lines, and approval of the figures is minuted. | Credit computation by line item; trial balance; board minute of 15 September 2025 | Strong |
Red flags
RED FLAGS · IE
Cloonmore Diagnostics Ltd
- IE07Subcontracted R&D and written notificationRed flag
The payment exceeds the greater of 15 per cent of the company's own R&D spend (€76,500) or €100,000, and there is no record that the university was told in writing it may not claim the credit.
- IE08Grant-funded expenditure excludedRed flag
The grant letter is on file but the qualifying expenditure on the Form CT1 was not reduced by the grant-assisted amount.
Draft response for IE07
DRAFT RESPONSE · IE07 · IE
Cloonmore Diagnostics Ltd
QUESTION
For payments to universities, institutes of higher education or unconnected third parties, whether the greater-of 15 per cent or €100,000 limits were applied separately, and whether each subcontractor was notified in writing that it may not claim the credit.
DRAFT
Stays in your account. Nothing is sent to Revenue.
Top fixes
Ordered by impact, then effort- FX1
Deduct the Enterprise Ireland grant relates to IE08
Reduce the qualifying expenditure by the €90,000 of grant-assisted costs, re-run the credit computation and amend the Form CT1 figures within the 12-month limit.
ImpactHighEffortLow - FX2
Apply the university limit and issue the notification relates to IE07
Restrict the University of Galway payment to €100,000, document the limit working against the company's own R&D expenditure, and record whether a written notification was given before payment or can be evidenced.
ImpactHighEffortLow - FX3
Rebuild time apportionment relates to IE05
Reconstruct the R&D time split from calendars, tracker history and lab schedules, and have the finance director confirm the percentages in writing with the basis stated.
ImpactHighEffortMedium - FX4
Document the overhead and cloud apportionment relates to IE06
Record the floor-area or headcount basis for the 40 per cent overhead allocation and remove cloud costs not wholly and exclusively incurred on R&D.
ImpactMediumEffortLow - FX5
Evidence the state of knowledge relates to IE04
Gather what can still be shown of the January 2024 search (emails, bookmarks, conference notes) and adopt a practice of saving search results at the start of each project.
ImpactMediumEffortMedium
See this for your own Ireland claim.
Start an assessment, answer the simulated questions and see where the file stands.