Skip to content
creditARMOUR home

Guides

United Kingdom: Additional Information Form and claim notification

Two forms decide whether a UK claim is valid before HMRC looks at a single project. This guide covers the claim notification for new or lapsed claimants and the Additional Information Form that every claim needs, and maps them to questions UK09 and UK10 in the mock audit.

Last updated

Claim notification

A company must submit a claim notification form if it is claiming for the first time, or if its last claim was made more than three years before the end of the claim notification period. The notification period runs from the first day of the accounting period to six months after the end of it.

The form asks for the company's details, the accounting period, a contact, any agent, and a brief summary of the planned R&D. It does not need the full narrative, but the summary should be consistent with what is later claimed.

If a notification was required and was not submitted in time, the claim for that period is invalid. The mock audit tests this at UK09 and treats a missing notification as a red flag.

  • Check the date of the company's last valid R&D claim
  • Diarise six months after the period end
  • Keep the HMRC acknowledgement with the claim file

The Additional Information Form

The AIF must be submitted before the company tax return that contains the claim. It names a senior officer responsible for the claim and any agent involved, lists the qualifying costs by category, and describes the projects: the field of science or technology, the baseline, the advance sought, the uncertainties and how the project tried to overcome them.

The number of project descriptions required depends on how many projects are in the claim. For up to three projects, all must be described. For more, the descriptions must cover at least half of the qualifying expenditure, with a minimum of three and a maximum of ten.

HMRC compares the AIF totals with the CT600 and the computation. Differences between them are a common reason for a compliance check. Question UK10 in the mock audit checks that the AIF exists, was submitted first, and agrees with the claim and the narrative.

  • Senior officer and agent named
  • Project descriptions cover the required share of expenditure
  • Cost categories agree to the computation and the CT600L
  • Submission acknowledgement dated before the CT600

Sequencing the forms and the return

The order is: claim notification (where required) within six months of the period end; Additional Information Form; then the CT600 with CT600L. An amended return to add a claim also needs the AIF first.

The mock audit asks for the dates of each step and flags any claim where the AIF date is after the return date or where the notification window was missed.

Key dates

StepWhenNote
Claim notificationWithin 6 months of the end of the accounting periodRequired for first-time claimants and companies that have not claimed in the previous three years.
Additional Information FormBefore the CT600 is filedMandatory for all claims. A claim without it is removed from the return.
Claim on the CT600Within 2 years of the end of the accounting periodAn original or amended return including the CT600L.
HMRC compliance checkUsually within 12 months of the filing date, longer if the return was filed late or a discovery appliesHMRC may ask for the records behind the AIF at any point during the enquiry window.

Mapped questions

This guide covers the following questions in the United Kingdom mock audit. A missing or late step here usually produces a red flag regardless of the project's merits.

  • UK09Claim notificationWhether a claim notification was required and, if so, submitted within six months of the end of the accounting period.
  • UK10Additional Information FormWhether the AIF was submitted before the CT600, is complete and is consistent with the claim and the narrative.

Official sources